Long Term Pumping Project Notes from 11-12-26

Meeting with Tom Wheat, Jason Weirsma, and JoAnne O’Rourke 11-12-26

Many residents from Eagle and Crooked attended…thank you!

*Status Update*
Crooked ran off and on this summer, Eagle ran all year, Crooked is 4″
below, Eagle is .25″ above
Big Rain this spring, 20 % wetter than normal
P&N and Drain Office are considering stopping the pump on Crooked, but are
waiting as Eagle is still running

*Changes Potentially Forthcoming*
EGLE permit for 800gpm, expected to be returned within a month
800 is to match Crooked output, so we can’t fill Crooked
800 gpm is variable, there will be a switch
There will also be a auto restart switch installed, which should
automatically try to restart without sending someone out
Pump will also have an auxiliary input to accommodate the extra 300 gpm, to
be determined how to filter that additional water

*Questions*

– Was it really running all year? Michelle L. challenged that, shuts off
every day
Tom didn’t officially mention it, but mentioned 74% as the possibly actual
runtime of the Eagle Pump

– Why can’t we get output rates and more Website info? Tom admitted that
there is more information from the reporting system used at the pump.
Jason conveyed that it was significant to gather and report on this, and
probaby wasn’t worth it, and that it might lead to him being called more
then now

– Jason and Tom mentioned multiple times that this system is unique to the
county, and they are still working through ‘kinks’

– Tom R asked about the financing. Jason said the initial cost was
8000/house, he thinks with FEMA and funding, it should be 4000/house, with
5-6 years of contingency for operation. He wouldn’t commit to refunds for
full pay residents

-Jason pointed out Drain Office would have constructed this, but Township
got the FEMA grant, so Drain Office had to supervise a Township project,
which has made this messy. He reiterated several times he will not take
possession until it is fully functional, and didn’t elaborate if that was
before or after the new changes

-No legal need to filter Eagle to Crooked, and the auxiliary input to the
Eagle pump was designed to be unfiltered initially. Crooked Lake had
significant concerns about this, and Jason said he would look into a
filter for the Auxiliary input, and stressed that if the pump was working
correctly at 500 gpm, the extra capacity might never be needed

-Jason has asked for a Green Light/Red Light on website that tells if the
pump is on. Ken confirmed that is it not on there currently

-Wetlands are filling, Leesa N (Crooked) pointed out the Bentwood easement
says the pumping has to stop if the wetlands gets to level, and that it is
close. Jason and Tom suspect it’s the 8th street culvert, that is managed
by the Road Commission, and that someone would follow up with them

-Financially, the project will be turned over to Jason once third party
audit is complete, it has already been audited by the Township

This is provided informationally, many of you that were there might have
more information, and hopefully there will be follow-up from the Township
and Drain Office

Thanks,
Eagle Lake Board

Board Update

Good Morning Eagle Lake!

The Board met Tuesday and elected new Officers for this year:

Debra Duncan – President
John Lauria – Vice-President
Cheryl Navoy – Treasurer
Aliya Patel – Secretary

Please support them as you have supported me these last few years. This
year, I will be taking care of the website and mailing lists, and
supporting Deb and John in their new roles. It’s been a pleasure being
President for the last few years, and I thank you all for helping us keep
this lake the wonderful place it is. There is still work to do with the
Long Term Project, but Deb has been engaged with the Board since the Flood
and we are in good hands. And I hope the switch to Progressive for our
Lake Management will continue to be a positive experience.

Enjoy the Weekend!
-Ken Toy

Lake Update – Harvesting June 12th

*Harvesting* – PLM was out this week, and it didn’t look like there was a
lot of excess floating up on shore. If you have any observations that we
can use the next time we have to decide to harvest or not, let us know
.

*Lake Level* – It had gotten down to +6.5LLL before these last batch up
storms, but they put us back up to +9LLL. After the Township, Drain
Office, and EGLE met this week, Tom Wheat is supposed to submit a report
back to the Township at their next meeting for how to proceed. While no
one from the Lake was invited, reports were that everyone was agreeable to
altering the permit to pump faster depending on the circumstances.

*Water Treatment* – PLM will be out 6/17 to treat mostly Lake 1. More
information can be found here
.

Enjoy the Warm Weather
-Eagle Lake Board

>
>

Lake Update – Harvesting June 8th

*Harvesting* – Progressive had observed some areas in their May 11th survey
that they suggested harvesting. The Board, as it was composed before the
Meeting, voted on whether to move forward with the harvesting. In a split
vote, it was approved. This area is mainly in the West Basin, and should
only be 20 hours of harvesting. This is a smaller effort, and one that we
can watch and take notes as to how it goes. It is also relatively cheap
compared to quotes from last year. They are scheduled to come out June 8th
and finish by June 9th. The treatment map can be found on our website:
https://eaglelakekzoo.com/lake-treatments-2026/

-Eagle Lake Board

Lake Update – June 1st

Lake Update – June 1stEagle Lake –

*Lake Level* is still slowly going down. Just over 7.5″ above LLL last
update. The Drain Commissioner reported that the pump is currently on.
There has been discussion between the Drain Office, EGLE, and the Township
about possibly having a higher pump rate in emergencies, the meeting is set
for June 8th and we will report back what comes of the meeting. The level
can be found here

.

*Election* – Congratulations to our new Board Members:
John Lauria – May 2026 – May 2029
Scott Ganton – May 2026 – May 2029
Debra Duncan – May 2026 – May 2029
Aliya Patel – May 2026 – May 2028
Nancy Desai – May 2026 – May 2027
We also thank Jay Hoffman, Judy Lewis, and Jason Machnik for their service.

More Update Soon after we elect Officers for this year.

-Eagle Lake Board

Progressive

 Eagle Lake has contracted with Progressive Companies for out Lake Management in 2026. The First Lake Survey is scheduled for May 11th, which will determine the treatment schedule for the summer Progressive FAQ Fertilizer FAQ

Live on the Lake

Thanks to these Artists for another Great Season!  Tom AskeyThe Kind BandSWB BandGreg & Tracy MusicKoz and the Effects  And Thanks for our Sponsors: Vineyard Assisted Living and Memory Care (Scott Ganton) Advantage Roofing (Tim Brown) Ken Toy & Amy Woznick